This Copy Toner Plant was built in 1994 and started operations in 1995 |
|
|
 |
Cost £13M to design, construct and commission the copy toner plant in 1994. |
|
|
|
 |
Current cost to build a new copy toner plant is approx. £18M |
|
|
 |
59,000 sq. ft. total building space |
|
|
|
 |
13,000 sq. ft. office/conference room/workshop area |
|
|
|
 |
20,000 sq. ft. of storage area |
|
|
 |
Operated at 500 kg/hr copy toner production |
|
|
 |
Highly automated (Allen-Bradley control system) |
|
|
 |
The copy toner plant produced black toner 8 micron spec and could be |
|
|
used for powder coatings . |
|
|
 |
The copy toner plant is in excellent condition and well maintained
|
|
|
 |
The copy toner plant operated a triple shift with (7) operation people
|
|
|
per shift, including team leader.
|
|
|
 |
The copy toner plant is situated on 3.5 acres, with on-site parking. |
|
|
|